What is a PD&E Study?

A Project Development and Environment (PD&E) Study is conducted to meet the requirements of the National Environmental Policy Act. During the study, we determine the location and conceptual design of feasible build alternatives for roadway improvements and their social, economic, and environmental effects. A PD&E study is finalized when the Federal Highway Administration, reviews the documentation and recommendations then provides a Location and Design Concept Acceptance.

Five Steps in the Transportation Development Process

The Transportation Development Process

  1. Long Range Planning: The FDOT and local governments conduct long-range transportation planning on an ongoing basis to identify and prioritize individual projects.
  2. Project Development and Environment Study (PD&E): During this step, design options and their social and environmental effects are examined.
  3. Design: During design, detailed construction plans are prepared.
  4. Right-Of-Way Acquisition: This phase entails acquisition of necessary right-of-way, based on the construction plans.
  5. Construction: The roadway is built during this phase.

The I-275/SR 93 project is in the PD&E study phase of the FDOT’s 5-step highway development process. A PD&E study assists the FDOT in determining the location, conceptual design and social, economic and environmental effects of the proposed improvement. During the PD&E study process, feasible alternatives are developed for roadway improvement projects. These “Build” alternatives are evaluated based on environmental, engineering and socioeconomic conditions, safety needs and public input. The need for additional right-of-way for stormwater and environmental mitigation is also evaluated during the PD&E study phase. The “No Build” alternative is considered to be a viable alternative and will remain so for the duration of the study.

If the study results in a “Build” alternative being selected, the project may proceed to the next phase, which is the Project Design phase.

What is a PD&E Study Reevaluation?

A reevaluation is the process used to document compliance with federal laws and to identify any changes that may have occurred since the approval of the original final environmental document. The reevaluation is needed for the purpose of updating the 1996 study, documenting changes in the current design standards, reassessing socio-economic and environmental impacts, and comparing any new alternative options with the previously approved roadway improvement.

What’s New?

The Florida Department of Transportation (FDOT) is conducting a Project Development & Environment (PD&E) Reevaluation Study for I-275 (SR 93) from south of 54th Avenue South to north of 4th Street North in Pinellas County. This project is a reevaluation of a PD&E study originally completed in 2016. A Public Hearing for the Reevaluation Study is anticipated for Spring 2019.

 

>> read more

Send us your Comments

Your comments are very important. You may send us your comments via the Comments page on this web site so that they can be considered as part of this study.

 

>> read more

Contact Information

For more information or to comment, please contact:

 

Ashley Henzel, P.E., Project Manager
Florida Department of Transportation, District Seven
11201 N. Malcolm McKinley Drive M.S. 7-500
Tampa, FL 33612-6456
Phone: (800) 226-7220 or (813) 975-6433
ashley.henzel@dot.state.fl.us


Kris Carson, Public Information Officer
Florida Department of Transportation, District Seven
11201 N. Malcolm McKinley Drive M.S. 7-500
Tampa, FL 33612-6456
Phone: (800) 226-7220 or (813) 975-6202
kristen.carson@dot.state.fl.us


Para preguntas en Español Valoramos la opinión del público sobre este proyecto. Si usted tiene preguntas o comentarios o si simplemente desea mas información en Español, favor ponerse en contacto con la señora Lilliam Escalera, E.I. al teléfono (813) 975-6445.


>> read more